Repairs are on the way for 17 railroad crossings all over Hall County, starting Tuesday and wrapping up March 21.
Norfolk Southern Railway, according to a press release from Hall County Spokeswoman Katie Crumley, advised the county on Friday that resurfacing will be taking place at the following locations (work dates in parenthesis):
- Yonah Homer Road, Alto (Feb. 16)
- Garland White Road, Alto (Feb. 16)
- Alto Village, Alto (Feb. 17)
- Grant Mill Road, Alto (Feb. 18)
- Wynn Shoals Road, Alto (Feb. 18)
- McDaniel Street, Alto (Feb. 22)
- Barefoot Road, Lula (Feb. 23)
- Chamblee Road, Oakwood (Mar. 3)
- Main Street, Oakwood (Mar. 7-8)
- White Sulfur Road (two crossings), Gainesville (Mar. 10-11)
- Cagle Road (two crossings), Lula (Mar. 15)
- Lula Road, Lula (Mar. 16)
- Athens Street, Lula (Mar. 16-17)
- 8th Street, Lula (Mar. 21)
- Barefoot Road, Lula (Mar. 21)
- Moccasin Gap, Lula (Mar. 21)
- Bertha Gragg Road, Lula (Mar. 21)
Crumley said drivers are advised to use caution if they drive through these areas while construction is taking place.