City audit singles out R&D Testing and Drilling
By
Posted 7:19AM on Wednesday 10th July 2002 ( 22 years ago )
ATLANTA - An audit report shows that Atlanta will have to spend an extra $6 million after paying nearly $8 million to remove contaminated soil from D.L. Stanton Park. <br>
<br>
The report - released Tuesday - says the City Council asked for the internal city audit in November, citing hefty project costs and questions about work done by the primary contractor, R&D Testing and Drilling. <br>
<br>
The firm was once owned by Samuel ``Rickey'' Rowe, a close friend of former Atlanta Mayor Bill Campbell. <br>
<br>
Auditors found that numerous purchasing laws were ignored when Rowe was awarded nearly $8 million to remove landfill materials from the 7.7 acre park. The work was awarded without bids or a formal contract. And, Rowe's company didn't have payment and performance bonds that the city code requires. <br>
<br>
Cleanup at the park was initiated in January 1999 after a girl was burned in a methane gas explosion in the soil. An investigation revealed that the park was built on a landfill. <br>
<br>
Campbell promised that the city would spend $1 million to fix the problem and reopen the park in a year. Auditors concluded that an annual citywide contract with R&D had expired in June 1999, before work began. <br>
<br>
Company officials say Rowe has sold his interest in the business, which filed for bankruptcy recently.