Coal ash disposal to cost $2 million, delay completion of seven dorms
By
Posted 2:58PM on Tuesday 21st May 2002 ( 23 years ago )
ATHENS - The disposal of coal ash found at the construction site of the University of Georgia's East Campus Village will cost between $1.9 and $2.7 million. <br>
<br>
The discovery of thousands of tons of coal ash will also delay construction of seven dormitories by at least a year, although construction on an 850-space parking deck at the new village began Tuesday. <br>
<br>
The UGA Real Estate Foundation had planned to finish the dorms for 1,200 students by summer 2003. <br>
<br>
The state Environmental Protection Division discovered the university dumping the coal ash in an unlined landfill in Oglethorpe County. <br>
<br>
Coal ash is not a hazardous waste but the state requires dumping it in a lined landfill because it can contain heavy metals and other contaminants. The EPD is monitoring removal to a lined county dump in Athens. <br>
<br>
The foundation plans to asks the state to pick up at least part of the bill to remove the ash.